Galeão - RJ

alt

 

Investments for the 2014 World Cup

Foreseen Actions:

- Rehabilitation of Passengers Terminal 1

Completion: July 2013

Status: Civil works under execution

- Rehabilitation of Passengers Terminal 2

Completion: October 2013

Status: Civil works under execution


- Recovery and revitalization of runways and ground areas systems

Completion: October 2013

Status: Civil works under bidding process

Total investment: R$ 813.27 million


 

Operacional Data
2011 2014
Passengers terminal (m2) 316.681 316.681
Capacity of terminal (year) 17.4 milion 44 milion
Demand Passengers/year 14.9 milion 18.7 milion
Airplanes Ground Area (m2) 712.895 712.895

 





 

 


 